Located on the boundary between the Northern and Brong Ahafo Regions,
Ghana's second largest hydroelectric generating station was
commissioned by the country's President, John Dramani Mahama, in
December 2013. Commissioning of the project means the country is one
step closer in its goal of becoming a major power producer in West
Africa.
The development of a hydropower scheme on the Black Volta
River at the Bui Gorge had been the subject of many studies; including
detailed studies by J.S. Zhuk Hydroprojeckt of the USSR in 1966, a
Feasibility Study by Snowy Mountains Eng. Corp (SMEC) of Australia in
1976 and another Feasibility Study by Coyne et Bellier in 1995, which
was subsequently updated in October 2006 to enable commencement of the
project.
The Bui Power Authority Act 2007 (Act 740) was enacted by
the Parliament of Ghana and assented by the President in July 2007 to
establish an Authority known as the Bui Power Authority (BPA) whose role
it was to plan, execute and manage the 400MW project.
Bui Dam - project description
The
Bui hydroelectric project consists of a roller compacted concrete (RCC)
gravity dam across the Black Volta and two Saddle Dams on the right
bank to contain the reservoir. The RCC dam has a five-bay spillway
arranged in the middle and a powerhouse located at the toe on the left
bank. The powerhouse has three generating units each with a capacity of
133.3MW. Power produced from the plant is evacuated from the newly
constructed Bui Switchyard through 161kV transmission facilities
operated as part of the National Interconnected Transmission System.
A
total of 240km of transmission lines has been built under the project.
These include two18km and 17km lines which broke into the existing
Sawla-Techiman lines to form Bui-Sawla and Bui-Techiman lines. Other
transmission facilities constructed are the 67km Bui-Kintampo line, the
138km Bui-Sunyani line, and expansion of the Sunyani Substation to
accommodate the new Bui-Sunyani line.
The Bui project is primarily
designed for hydropower generation. It also includes the development of
an irrigation scheme for agricultural development, and measures to
enhance ecotourism and fisheries. It also included a Resettlement and
Community Support Program.
The project has led to the resettlement
of seven communities with a total population of 1216. The resettlement
program has been divided into three parts. The first part (Part A)
involved settlement of communities that were living within the project
construction area. For this reason, the resettlement of these
communities was undertaken prior to the commencement of construction
activities. The second part (Part B) involves the resettlement of
communities that resided at locations that were inundated when the
impoundment begun in 2011. The third and final part (Part C) involves
the resettlement of the Bui Camp, the current residence of personnel of
the Game and Wildlife Division of the Forestry Commission which have
been assigned to protect the Bui National Park.
The project also
included the construction of a bridge across the Black Volta River
downstream of the dam to facilitate the movement of personnel,
agricultural produce and improve access to markets for the communities
in the project area.
Implementation
The project was
implemented under an Engineering, Procurement and Construction
(EPC)/Turnkey Contract awarded to Sinohydro Corporation Limited of
China. The works were supervised by Bui Power Authority (BPA) with the
assistance of an Engineering Consultant; Tractebel Engineering/Coyne et
Bellier.
The project implementation commenced with detailed
geological and hydro geological investigations. These were carried out
between October 2007 and March 2008.
Construction Phase I
(Preparatory works) which included the erection of temporary facilities
and support services required for the dam construction commenced in
January 2008 and were completed in December 2008.
Construction
Phase II (Main works) commenced in January 2009. Impoundment began 30
months after start of construction on 8 June 2011. The reservoir is
designed to have a full supply level of 183m asl and an associated
maximum surface area of 444km2. It was expected that the reservoir,
would require at least two rainy seasons after river impoundment to
build up sufficient head for the commencement of power production. In
the 2011 rainy season, the reservoir level rose from about 100m to about
132m. After the 2012 rainy season, the reservoir had as expected
attained 169.7m asl which was sufficient to enable commissioning of the
generating plant.
After dry and wet tests were successfully
carried out, the three generating units were commissioned in May, July
and November 2013 respectively. Other associated and non-power works on
the project will be completed by mid 2014.
Completion of the
project provides Ghana with an additional 400MW (20% increment) of
installed capacity with average annual generation of 1000GWh.
Project benefits
Power supply
The 400MW plant will increase the country's generation capacity by about 20% and improve reliability and security of power supply to the Northern sector of the country.
The 400MW plant will increase the country's generation capacity by about 20% and improve reliability and security of power supply to the Northern sector of the country.
The infrastructural additions to the
National Interconnected Transmission System will also increase the
capacity and quality of electricity service delivery in the Brong-Ahafo,
Northern, Upper East and Upper West Regions of the Country.
Provision
of Ancillary Services from the Bui Plant - i.e. Peaking Power and
Reactive Power - will improve the voltage profile and power factor of
the power system and in so doing also reduce transmission losses.
Agriculture
The potential development of about 30,000 ha of irrigable land could form the bedrock for massive mechanized farming to improve the production of food and cash crops. The Lake that has been formed also presents the potential for enhancing the fisheries resources of the Black Volta River and increasing the yield.
The potential development of about 30,000 ha of irrigable land could form the bedrock for massive mechanized farming to improve the production of food and cash crops. The Lake that has been formed also presents the potential for enhancing the fisheries resources of the Black Volta River and increasing the yield.
Socio-economic
The project has provided opportunities for employment both during project construction and thereafter, and offers improvement in educational, health and social facilities and services to nearby communities is part of the project. A further benefit of the project is improved potable water supply for domestic use.
The project has provided opportunities for employment both during project construction and thereafter, and offers improvement in educational, health and social facilities and services to nearby communities is part of the project. A further benefit of the project is improved potable water supply for domestic use.
No comments:
Post a Comment