A long simmering turf war for control over associated gas from the 
jubilee fields could be playing out on the eve of the first processing 
of the commodity from the oil fields.
The Ghana National Petroleum Corporation (GNPC) has confirmed to The 
Chronicle, a media report that the Jubilee partners are 'demanding' a 
full audit of the gas processing plant before it is connected to the 
floating vessel, FPSO Kwame Nkrumah, offshore.
State newspaper Daily Graphic, quoting sources close to the project, 
reported that an initial plan to create a by-pass to carry gas onshore 
from the FPSO to pipelines leading to the Aboadze Thermal Plant was 
ignored by Ghana Gas Company, despite huge investments made by the 
partners in purchasing equipment for that purpose.
This has raised fears of further delays in the country's quest to 
deliver gas from the fields for cheaper power generation. The 
Communications Manager at the GNPC, who confirmed the report to The 
Chronicle, said the audit was only "a common sense approach" to testing 
the integrity of the facility for safety reasons.
But, Dr. George Sipa Yankey, explained that the by-pass idea could 
have extended the delivery period of the gas from the field for another 
nine months.
 He said the need for the by-pass was part of the initial 
plan, but noted that the partners could not readily get a heater 
component to regulate the heat for Aboadze to receive the gas, as 
initially anticipated.
Secondly, there was a need for a more detailed engineering works to 
be done before the by-pass could be constructed, due to the fact that 
the plant's systems are computerized, and the by-pass facility needed to
 be configured into them. Thirdly, the gas pipelines were not designed 
to take wet gas straight from the fields, noting that this could pose 
some serious challenges for the power plants.
He further explained that the idea of the by-pass was within the 
programme of the Ghana Gas Company, but due to constraints with getting 
the heater component, it was decided to construct it to coincide with a 
turbo expander project to help save the plant in the event of upset 
conditions, and also ensure continued gas flow even during plant 
maintenance.
He insisted that the company was in constant touch with the lead 
partners, Tullow, to get the by-pass done. Speaking on the subject of an
 audit, he said the impression being created by a section of the public,
 who remain skeptical about the project, to the effect that Tullow was 
demanding an audit was not true, as an agreement had long been reached 
for the audit to be done.
To this effect, he said, the quality assurance group of Sinopec, the 
company working on the project, will be coming to assess the project by 
next week.
Furthermore, an independent party would also be conducting an audit 
this month. "It is the taxpayers' money, and we want everything to be 
okay," he emphasised. He noted further that all components at the plant 
are all captured at a motor control center to detect problems and either
 solve them or prompt for personnel to be sent to fix it. "You see, 
people do not appreciate that the system is computerised."
Bernice Natue, Communications & Investor Relations Manager, 
Tullow Ghana Limited, in an email correspondence to The Chronicle on the
 issue, said, "To the best of our knowledge, the by-pass project is on 
hold until the completion of the main plant."
She explained that an independent audit is required as part of the 
regular assurance procedure associated with engineering projects of such
 nature, as it will assure the integrity of the Gas Processing Plant 
(GPP) and certify that it is safe and ready to receive hydrocarbon gas.
"Tullow is committed to adhering strictly to international safety 
standards and local regulations, and will continue to work with partners
 in the project to ensure that gas is exported from the Jubilee Fields 
to the GNGC facility at Atuabo safely for the mutual benefit of all 
concerned," she said.

 
 
No comments:
Post a Comment